Bond Progress Report 2022

Written by
Rate this item
(0 votes)

2021 Bond Progress Report

On November 2, 2021, Weber County voters approved a $279 million school bond.  The bond passed with 60.51% of voters voting for the issuance of bonds.

The following projects are included on the 2021 bond:

  • New high school in Taylor:  $157 million
  • New junior high school in West Haven:  $51 million
  • New elementary school in West Haven:  $34 million
  • Rebuild of Roosevelt Elementary in Washington Terrace:  $37 million

Estimated start and completion dates:

  • High School
    • Start: November 2021
    • Completion: July 2024
  • Junior High
    • Start: March 2022
    • Completion: July 2024
  • Elementary
    • Start: October 2022
    • Completion: July 2024
  • Roosevelt
    • Start: January 2024
    • Completion June 2026

Issuance of bonds:

  • 1st issuance: $90 million (January, 2022)
  • 2nd issuance: TBD
  • 3rd issuance: TBD

High School

  • Budget $157 million
  • Selection of architect - MHTN Architects
  • Selection of general contractor - Hogan & Associates Construction
  • Construction begins - March 2022
  • Selection of name, mascot and colors - May, 2022
    • West Field High School
    • Longhorns
    • Burnt orange, black, silver & white
  • Estimated completion date - July 2024
  • Boundary adjustments - TBD
  • Final cost -TBD

BondProgress

 

 

BondProgress1

Junior High School

  • Budget $51 million
  • Selection of architect - Design West Architects
  • Selection of general contractor - Hogan & Associates Construction
  • Construction begins - March 2022
  • Selection of name, mascot and colors - TBD
  • Estimated completion date - July 2024
  • Boundary adjustments - TBD
  • Final cost - TBD

Elementary School

  • Budget $34 million
  • Selection of architect - MHTN Architects
  • Selection of general contractor - Westland Construction
  • Estimated start date - October 2022
  • Selection of name, mascot and colors - TBD
  • Estimated completion date - July 2024
  • Boundary adjustments - TBD
  • Final cost - TBD

Roosevelt Elementary

  • Budget $34 million
  • Selection of architect - MHTN Architects
  • Selection of general contractor - Hogan & Associates Construction
  • Estimated start date - January 2024
  • Estimated completion date - July 2026
  • Final cost - TBD

 

 

Read 65014 times Last modified on Tuesday, 05 July 2022 13:45