Bond Progress Report 2022

2021 Bond Progress Report

On November 2, 2021, Weber County voters approved a $279 million school bond.  The bond passed with 60.51% of voters voting for the issuance of bonds.

The following projects are included on the 2021 bond:

  • New high school in Taylor:  $157 million
  • New junior high school in West Haven:  $51 million
  • New elementary school in West Haven:  $34 million
  • Rebuild of Roosevelt Elementary in Washington Terrace:  $37 million

Estimated start and completion dates:

  • High School
    • Start: November 2021
    • Completion: July 2024
  • Junior High
    • Start: March 2022
    • Completion: July 2024
  • Elementary
    • Start: October 2022
    • Completion: July 2024
  • Roosevelt
    • Start: January 2024
    • Completion June 2026

Issuance of bonds:

  • 1st issuance: $90 million (January, 2022)
  • 2nd issuance: TBD
  • 3rd issuance: TBD

High School

  • Budget $157 million
  • Selection of architect - MHTN Architects
  • Selection of general contractor - Hogan & Associates Construction
  • Construction begins - March 2022
  • Selection of name, mascot and colors - May, 2022
    • West Field High School
    • Longhorns
    • Burnt orange, black, silver & white
  • Estimated completion date - July 2024
  • Boundary adjustments - TBD
  • Final cost -TBD

BondProgress

 

 

BondProgress1

Junior High School

  • Budget $51 million
  • Selection of architect - Design West Architects
  • Selection of general contractor - Hogan & Associates Construction
  • Construction begins - March 2022
  • Selection of name, mascot and colors - TBD
  • Estimated completion date - July 2024
  • Boundary adjustments - TBD
  • Final cost - TBD

Elementary School

  • Budget $34 million
  • Selection of architect - MHTN Architects
  • Selection of general contractor - Westland Construction
  • Estimated start date - October 2022
  • Selection of name, mascot and colors - TBD
  • Estimated completion date - July 2024
  • Boundary adjustments - TBD
  • Final cost - TBD

Roosevelt Elementary

  • Budget $34 million
  • Selection of architect - MHTN Architects
  • Selection of general contractor - Hogan & Associates Construction
  • Estimated start date - January 2024
  • Estimated completion date - July 2026
  • Final cost - TBD

 

 

Thursday, 26 May 2022 14:02

Account Retention Information

As of October 1, 2022, retiree WSD accounts will be terminated. This includes Employee Online. 

What does this mean?

You will no longer be able to access information housed in Employee Online (paycheck stubs, W-2’s,etc.) If you need to access information from Employee Online after October 1, 2022, contact Human Resources at 801-476-7886.

Will I have access to my WSD email account or information on Google Drive?

If you are not actively working for WSD, your WSD email account and Google Drive will no longer be available. Please provide the district with a personal email address by September 30, 2022, in order continue receiving communication regarding your health insurance benefits.  

How do I provide the district with a personal email address?

  1. Log into Employee Online
  2. Click “Menu” (top left hand corner)
  3. Click “Personal Information”
  4. Click “Personal Information” under Employee column
  5. In the Personal Email Box- type your personal email address

How do I move documents or information saved from my email and Google Drive?

While you may be leaving, your files stay here, but there is a way to take them with you! You can download or transfer your emails, files, notes, and more with Google Takeout. Follow along with Ryan in the video below:

 

 

Tuesday, 24 May 2022 07:51

Fees

Fee Schedules 2023-24

2023-24 Fees2023-24 Fees

Fees/Waivers/Fundraising Training 2022-2023

This training is for all district employees who work with student fees or fundraising.  

https://youtu.be/eouaOWMR00U

 

Fees Schedules 2022-2023

School Fees and Waivers

Wednesday, 20 April 2022 11:00

Meal Prices 2024-25

Meal Prices for 2024-2025 -

  Lunch Prices Breakfast Prices
Per Meal Elementary Jr High High School Elementary Jr High High School
Paid $2.10 $2.60 $2.60 $1.60

$1.85

$1.85
Reduced $0.40 $0.40 $0.40 $0.30 $0.30 $0.30
1st Quarter - 49 days            
Paid $102.90 $127.40 $127.40 $78.40 $90.65 $90.65
Reduced $19.60 $19.60 $19.60 $14.70 $14.70 $14.70
2nd Quarter - 43 days            
Paid $90.30 $111.80 $111.80 $68.80 $79.55 $79.55
Reduced $17.20 $17.20 $17.20 $12.90 $12.90 $12.90
3rd Quarter - 48 days            
Paid $100.80 $124.80 $124.80 $76.80 $88.80 $88.80
Reduced $19.20 $19.20 $19.20 $14.40 $14.40 $14.40
4th Quarter - 40 days            
Paid $84.00 $104.00 $104.00 $64.00 $74.00 $74.00
Reduced $16.00 $16.00 $16.00 $12.00 $12.00 $12.00
             
Adult Meals $4.25 $4.25 $4.25 $2.50 $2.50 $2.50

2nd Meals cost $4.25 each for everyone! - The Federal Government does not reimburse 2nd meal

North Fork Meal Prices 2023-24

  Dinner
Per Meal Elementary Jr High High School
 Paid $4.00 $4.00 $4.00
       
Adult Meals $4.50 $4.50 $4.50

Payment Options

Credit Card

A credit card can be taken in the office with the secretary or book keeper. Credit card payments will no longer be accepted over the phone.

Pay Online

Pay for your student's lunch online with your credit card. The service is easy to use, convenient, private and secure. Once you log in to PowerSchool, click on "Purchases and Payments" on the left side of the screen.

Login to Powerschool

Pay By Check

Make check payable to (School Name) and bring the check to the Food Service Manager's Office. A local address and phone number are required to be either printed or handwritten on the check. The student(s) full name and grade are required on the check memo line.

Pay With Cash

Cash may be brought to the Food Service Manager's office for deposit on the student's account, or students may pay cash daily through the serving line.

 

 

YouthBuild is a group that provides students that are disconnected from a traditional education to be able to reconnect, gain a high school diploma and gain trade skills. These students built chairs and donated them to North Ogden Elementary. Students that delivered the rocking chairs were Levi Gibson, Eder Charles King, Alex Prescott, Jaxsen Clark, Michael Rodas, James Salas, Christian Johnson and staff William Nielsen, Gavin Leavitt. We love their craftsmanship and celebrate their skill.

Youthbuild students sitting in the chairs they made.

 

Wednesday, 19 January 2022 10:00

Family Code Night

Weber School District 
Family Code Night

Presented by Weber School District & Skill Struck

Weber School District is excited to invite families of students in grades 3-6 to attend an amazing and informative coding night with Skill Struck. Skill Struck is the computer science program that is being introduced in the elementary schools. Instruction will be provided in both English & Spanish.

When:

January 27, 6-8 PM
Wahlquist Junior High
2656 N 2400 W

Details:

Dinner Provided
Join us from 6:00-6:30 PM for a quick bite before the workshop begins.

Chromebooks
A Chromebook will be provided.

Virtual Option
Scan the QR code to register for the link.

This experience is best suited for just you and your grades 3-6 child.

Email Melissa Hadley at  with questions.

Family Code Night Jan 20Code Night Spanish January 20

 

 

 

Tuesday, 07 December 2021 02:18

Lakeview celebrates all the holidays

We are celebrating all the holidays in December! On December 3rd, it was "National Roof Over Your Head Day". We discussed why we need a roof, how roofs keep us safe, and then how a roof is built. Students thought like engineers and designed their own roof. Then, they used graham crackers, frosting and candy to build their own gingerbread house roof!

Page 10 of 138