Projects |
Construction Bid |
Construction Start |
Expense as of 5/8/2024 |
Estimated Construction End |
Estimated Final Cost |
West Field HS (New Build) |
$154,431,924 |
2/1/2022 |
$122,550,443 |
August 2024 |
$154,431,924 |
Mountain View JHS (New Build) |
$62,688,570 |
4/22/2022 |
$55,765,214 |
August 2024 |
$62,688,570 |
Haven Bay Elem. (New Build) |
$42,741,300 |
3/1/2023 |
$24,246,207 |
August 2024 |
$42,741,300 |
Roosevelt Elem. (Replacement) |
$46,393,324 |
12/20/2023 |
$2,605,300 |
August 2025 |
$46,393,324 |
Total |
$306,255,118 |
|
$205,167,164 |
|
$306,255,118 |