Projects | Construction Bid | Construction Start | Expense as of 5/8/2024 | Estimated Construction End | Estimated Final Cost |
West Field HS (New Build) | $154,431,924 | 2/1/2022 | $122,550,443 | August 2024 | $154,431,924 |
Mountain View JHS (New Build) | $62,688,570 | 4/22/2022 | $55,765,214 | August 2024 | $62,688,570 |
Haven Bay Elem. (New Build) | $42,741,300 | 3/1/2023 | $24,246,207 | August 2024 | $42,741,300 |
Roosevelt Elem. (Replacement) | $46,393,324 | 12/20/2023 | $2,605,300 | August 2025 | $46,393,324 |
Total | $306,255,118 | $205,167,164 | $306,255,118 |