2021 Bond Progress Report
On November 2, 2021, Weber County voters approved a $279 million school bond. The bond passed with 60.51% of voters voting for the issuance of bonds.
The following projects are included on the 2021 bond:
- New high school in Taylor: $157 million
- New junior high school in West Haven: $51 million
- New elementary school in West Haven: $34 million
- Rebuild of Roosevelt Elementary in Washington Terrace: $37 million
Estimated start and completion dates:
- High School
- Start: November 2021
- Completion: July 2024
- Junior High
- Start: March 2022
- Completion: July 2024
- Elementary
- Start: October 2022
- Completion: July 2024
- Roosevelt
- Start: January 2024
- Completion June 2026
Issuance of bonds:
- 1st issuance: $90 million (January, 2022)
- 2nd issuance: TBD
- 3rd issuance: TBD
High School
- Budget $157 million
- Selection of architect - MHTN Architects
- Selection of general contractor - Hogan & Associates Construction
- Construction begins - March 2022
- Selection of name, mascot and colors - May, 2022
- West Field High School
- Longhorns
- Burnt orange, black, silver & white
- Estimated completion date - July 2024
- Boundary adjustments - TBD
- Final cost -TBD
Junior High School
- Budget $51 million
- Selection of architect - Design West Architects
- Selection of general contractor - Hogan & Associates Construction
- Construction begins - March 2022
- Selection of name, mascot and colors - TBD
- Estimated completion date - July 2024
- Boundary adjustments - TBD
- Final cost - TBD
Elementary School
- Budget $34 million
- Selection of architect - MHTN Architects
- Selection of general contractor - Westland Construction
- Estimated start date - October 2022
- Selection of name, mascot and colors - TBD
- Estimated completion date - July 2024
- Boundary adjustments - TBD
- Final cost - TBD
Roosevelt Elementary
- Budget $34 million
- Selection of architect - MHTN Architects
- Selection of general contractor - Hogan & Associates Construction
- Estimated start date - January 2024
- Estimated completion date - July 2026
- Final cost - TBD